Senior Engineer, Phil Coggin, was flown – as the only passenger of a chartered flight - by our customer Resolute Mining to their Syama mine in Mali to provide lift planning and supervision services for a construction project there.

The construction - a giant chimney – is a rather unusual construction on a mine site; the Syama mine has a special process where the ore is roasted before processing through the CIL tanks.

The chimney had a total height of 74m. The crane – a GROVE GMK 6300 – was hired from Global Construction Afrique – had a 54m boom plus a 35m fixed jib giving us a total length of 89m. The lower sections were built in 12m lengths, then the higher lengths in 6m sections weighing in at 6t each with a 2m cap at 2.4t. Tip height was 91m and we were working at 20m radius.

We are pleased to report that the lift was flawless.

 

 

 

Categories:
  • Ghana Gas: Atuabo

    Ghana Gas: Atuabo

    A complex lift for Ghana Gas called a "magnificent performance" by customer, Jon Moore.

    Read more

  • Newmont Mine: Ghana

    Newmont Mine: Ghana

    Tandem lift using 250 and 170 tonne crawler cranes. Weight of load: 110. Plan and execution to move Liebherr face…

    Read more

  • SAM_1410

    Boat Loading: Ghana/Liberia

    Boat-side load supervision for two cranes and a forklift truck, Takoradi Ghana.

    Read more

  • P1020381

    Forklift Training: Accra, Ghana

    Testing Excerpt Vodafone Training

    Read more